Schedule Performance Index (SPI)

A measure of schedule efficiency on a project. It is the ratio of earned value (EV) to planned value (PV).

SPI = EV divided by PV.

An SPI equal to or greater than one indicates a favorable condition and a value of less than one indicates an unfavorable condition.

[ PMBOK ]